Full road closures next week for carriageway treatments

Full road closures next week for carriageway treatments

Surface dressing is due starting next week, subject to weather conditions, will see full road closures around the area as part of the carriageway surface treatment programme.

This phase of work includes applying a bitumen emulsion spray to the road, followed by a layer of stone chippings which are spread and rolled into the existing road surface.

This process seals the existing surface from water, improves the surface texture and extends the life of the road.

Following this will be a second treatment which is undertaken approximately 10 days after the first treatment. The function of this is to lock the stone chippings into the new road surface, minimising any loose material.

To allow the works to be completed and to ensure the safety of those completing the works, a full road closure will be in place on the day between 7.30am and 6pm.

Works may not take the full day to complete, depending on the length of the street, but once complete, the road will be reopened as soon as possible.

The following streets are scheduled to be included in the programme of works:

Elderberry Way – Monday 6 June
Redwood Drive – Monday 6 June
Larch Road – Monday 6 June
Beaufort Crescent – Monday 6 June
Pytchley Walk – Monday 6 June
Fitzwilliam Mews – Monday 6 June
Hollingsworth Close – Monday 6 June
Buck Beck Way – Monday 6 June
Ash Court – Monday 6 June
Pine Court – Monday 6 June
Beech Way – Monday 6 June
Walnut Crescent – Monday 6 June
Oak Way – Monday 6 June
Belvoir Road – Monday 6 June
Lansdown Link – Monday 6 June
Brampton Way – Monday 6 June
Raven Hill Close – Monday 6 June
Belmont Close – Monday 6 June
Ashby Road – Tuesday 7 June
Ormsby Close – Tuesday 7 June
Irby Court – Tuesday 7 June
Swaby Drive – Tuesday 7 June
Ann Grove – Tuesday 7 June
Solomon Court – Tuesday 7 June
West Street – Tuesday 7 June
Glebe Road – Tuesday 7 June
Kew Road – Tuesday 7 June
Crow Hill Avenue – Tuesday 7 June
William Street – Tuesday 7 June
George Street – Tuesday 7 June
Oslear Crescent – Tuesday 7 June
Coulbeck Drive – Tuesday 7 June
Curzon Court – Tuesday 7 June
Hey Street – Tuesday 7 June
Parker Street – Tuesday 7 June
Sherburn Street – Tuesday 7 June
Whites Road – Tuesday 7 June
Barkhouse Lane – Tuesday 7 June
Bark Street – Wednesday 8 June
Thrunscoe Road – Wednesday 8 June
Albert Road – Wednesday 8 June
Humber Street – Wednesday 8 June
Highgate – Wednesday 8 June
Elm Avenue – Wednesday 8 June
Reynolds Street – Wednesday 8 June
Blundell Avenue – Wednesday 8 June
Hart Street – Wednesday 8 June
Great Coates Road – Wednesday 8 June
Maple Grove – Wednesday 8 June
Cedar Drive – Wednesday 8 June
Oaklands Road – Wednesday 8 June
Spinney Close – Wednesday 8 June
Beechwod Avenue – Wednesday 8 June
Woodlands Avenue – Wednesday 8 June
Rose Gardens – Thursday 9 June
Leyden close – Thursday 9 June
Chilton Close – Thursday 9 June
Bradford Road – Thursday 9 June
Ainsworth Road – Thursday 9 June
Holbeck Place – Thursday 9 June
Morton Close – Thursday 9 June
Clyfton Crescent – Thursday 9 June
Balfour Place -– Thursday 9 June
North Moss Lane – Tuesday 14 June

On street parking will need to be suspended to allow the works to take place.

North East Lincolnshire Council said: “Residents are asked to kindly avoid parking vehicles on the road or footpath in the immediate location to ensure a safe working area can be maintained. Access for emergency vehicles will be maintained at all times.

“Advanced warning signs will be in place to advise road users of the upcoming works dates.

“To avoid the build-up of loose materials on the highway, the contractor will return to sweep up loose materials after a few days. Residents are asked to move their vehicles from the road if they see the road sweeper return to allow as much excess material to be collected as possible.

“The council, EQUANS, and the contractor Kiely Bros would like to apologise in advance for any inconvenience this may cause.”